The Voice of Distributed Energy
Menu
  • Stories
    • Distributed Generation
    • Storage & EVs
    • Virtual Power
    • Energy Efficiency
    • Policy
    • Microgrids Now
    • Prosumers
    • Decentralized Grid
  • Podcast
  • Resources
    • White Papers
    • Case Studies
    • Content Services
  • About
  • Newsletter
  • Substack
Energy Changemakers
Subscribe
Featured

Are Data Centers Raising the Bridge?

by Elisa Wood

data center onsite power
Baturina Yuliya/Shutterstock.com
October 11, 2026
Share

The bridge-to-grid concept started as a workaround for data centers that couldn’t connect to the grid immediately. They chose to install onsite power to bridge the gap until the grid was ready.

That makes sense if the wait is a couple of years. But large-load connections can require transmission and substation upgrades that push wait times to 10 years or longer.

This is causing some data center developers to raise the bridge — stop thinking of onsite power as a temporary solution and instead design for the long term.

How long is the wait really?

“You can build a data center in 18 to 24 months, but they’re looking at backlogs of five to six to 10 years to get the power,” said Stuart Adam, head of natural resources at global insurer Howden US.

One prospective project in PJM territory was given a 15-year timeline for utility service, according to Emily Kunkel, associate principal at engineering firm Thornton Tomasetti.

Support our work with a free or paid subscription

“I’m not even going to call it bridge to grid,” said Kunkel. Bridge to grid assumes utility service will arrive within about five years, she said. In some cases, the approach becomes “let’s build behind the meter, hope for bridge to grid.”

Faced with these delays, some may abandon the bridge concept entirely.

“We believe going ‘off grid’ will become more common for inference data center and commercial & industrial (C&I) customers,” wrote Morgan Stanley in an Oct. 6 report, Living on the Edge: The Rise of Distributed Power.

While the grid or large independent power plants may remain the best option for mega campuses, the report says distributed energy suits edge computing, a growing approach that processes data closer to where it’s used.

“A bridge is supposed to end,” said James Mercer, principal at Metro Colo Advisory, an independent data center advisory practice. “When the utility date slides past the first five years of a fifteen-year lease, the onsite plant isn’t a bridge anymore. It’s the primary power for a third of the deal, and it should be designed, permitted and contracted that way from day one.”

Mercer also cautions developers to be realistic about when grid power will arrive. “Most sites marketed as ‘powered’ are further from power than the listing suggests,” he said. “A load letter or a queue position is not a date, and the bridge decision should start from what the utility has committed in writing.”

Whether short-term or long-term, onsite power use by data centers is on the rise. Energy intelligence firm Enverus now forecasts that of the 83 GW of new US data center load expected by 2030, 41% (34 GW) will be served by behind-the-meter power, up from 22.5 GW in its earlier forecast. Most of those projects still plan some form of grid connection, according to Enverus senior analyst Alex Nevokshonoff. But fully off-grid data centers, barely discussed a year ago, are now emerging, he says in an upcoming Energy Changemakers podcast.

With the bridge gone, then what?

Redefining an onsite plant as a long-term asset, rather than a short-term bridge, changes its financing, design and engineering requirements — as well as its economic profile. Equipment selected for speed-to-power isn’t necessarily the best choice over many years.

“As you start to look at that 8-15-year timeline, you would really want to change the technology that you’d be using because you’d want that longer-term, more efficient energy,” Kunkel said. This requires layering in different or additional technologies that combine early speed-to-market with a lower price for power delivered later.

Simple-cycle gas turbines and reciprocating engines offer speed. But Kunkel said some developers start with simple-cycle turbines and later add a steam cycle, converting them into a more efficient combined-cycle plant.

Other configurations combine gas generation with batteries, solar or fuel cells. Kunkel considers these fully islandable systems microgrids, even at hundreds of megawatts.”It’s a macro microgrid,” she said.

Batteries help manage rapid changes in AI power demand while letting generators run more steadily.

The economics change with time

data center onsite power

A developer expecting to operate onsite generation for two or three years might accept higher electricity costs in exchange for faster market entry. But costs can accumulate when a two-year bridge morphs into a 10-year power strategy.

A Rabobank analysis finds that gas reciprocating engines and aeroderivative turbines carry a structural cost penalty over long periods, largely because continuous use triggers major overhauls and rebuilds about once a decade. Five years into operation, they produce electricity at an estimated $106 to $107/MWh, compared with roughly $86/MWh for average industrial grid power — a premium of about 24%. Costs dip in later years, then jump again when rebuilds come due, according to the analysis.

Combined-cycle plants follow a different path. Rabobank finds their costs fall to roughly $55/MWh by year 15, and by year 20 they cost about one-third less than gas engines, which supports Kunkel’s case for changing technology as the timeline stretches.

Metro Colo Advisory calculated what the gas-engine premium means for a 50-MW data center running at an 80% load factor:

“On a 50 MW campus, the gap between on-site gas and grid power is about seven million dollars a year. For two years, that is the price of speed. For six years it is forty-two million dollars, and it deserves the same engineering scrutiny as the building,” Mercer said.

Those figures are illustrative, not a project-specific forecast. Actual costs depend on fuel contracts, equipment selection, financing, and utility rates. And they don’t account for the value of getting expensive AI computing equipment operating years earlier.

The Rabobank analysis also points out that renewable energy faces no long-term fuel constraint and becomes more valuable over time. Solar PV reaches roughly $49/MWh at year 15 and $34/MWh by year 30. Renewables offer the most favorable long-run cost trajectory, the report says, but data centers also require firm generation or grid supply to meet the reliability needs, says the report.

The move toward renewables may accelerate over time. “Hyperscalers have very public decarbonization objectives; thus far, they have been willing to accept gas generation technology as a means to gain speed. Over the longer term, the expectation may be to incorporate greener technology,” Kunkel said.

Operating a power plant is different from owning backup generators

Running onsite generation for years rather than months also changes operational requirements.

Maxwell Spaeth, director of business development, U.S., at Equans Services, said operators should consider long-term fuel contracts, redundancy, maintenance, environmental permitting and emissions compliance, and future capacity needs.

Equipment may need more frequent servicing and inspection if it was designed for emergency backup but is used frequently instead.

Securing fuel also becomes a bigger challenge, since gas pipelines face their own development delays.

Kunkel said independent power developers and landowners are increasingly assembling these projects, offering data centers land, natural gas access and power purchase agreements.

What happens when the grid finally arrives?

Data centers also need to plan what they will do with the onsite energy system when the grid finally arrives.

“Do I maintain my power purchase agreement with this new behind-the-meter power plant, or do I just go back to a traditional grid operator?” Kunkel asked.

A data center might continue buying onsite electricity, retain the plant for backup or sell its output into wholesale markets once utility service arrives.

Kunkel said efficiency matters particularly in that last scenario. An inefficient simple-cycle plant built for speed could struggle to compete in wholesale markets, while a more efficient plant could have a longer economic life.

Owners are also considering how these assets might eventually support peak shaving, resilience or campus expansion, making them more useful over the long term, according to Babatunde Ukwu, business development director for energy and industrial at Equans Services, an energy and facilities services company.

Is the grid moving further out of reach?

The gap isn’t likely to close soon between data center demand and the grid’s ability to serve it. Utilities face a parts problem. Equipment to expand the grid is in short supply and getting more expensive.

Parag Nathaney, a utility engineer and power market analyst, cited a rise in new gas combined-cycle costs from 1,200–1,500/kW in 2022 to 2,000–2,500/kW in 2025, and order reservations for new equipment, like gas turbines and transformers, extending through 2030–2032.

State and federal policy swings and market design changes that discourage investors compound the problem, he said. Meanwhile, data center construction, behind-the-meter generation for hyperscalers, and tax-credit-backed battery projects compete for the capital and developers that might otherwise build grid-connected generation.

Another wrinkle: If more data centers pursue self-supply, it could complicate transmission planning, which relies on forecasts of where grid-served demand will appear. Onsite plants that also send power to the grid could change the system’s topology and require closer coordination between utilities and data centers. One option, Nathaney suggested, is for utilities to steer data centers to grid nodes with spare capacity. Utilities could even auction that headroom, much as they sell pipeline capacity, to ease interconnection and planning delays.

For now, the question is whether onsite power becomes a permanent fixture of data center development or continues to act as a workaround until the grid catches up.

“One of the major issues with the long grid interconnection delay is that it is impossible to predict what will be at the other end of the wire 10 years from now. To mitigate this risk, utility and data center operators should agree on a go/no-go timeline as an inflection point for diminishing returns,” Kunkel said.

Morgan Stanley Puts a Price on Speed to Power — and Distributed Energy Wins Big

The findings challenge a longstanding assumption in the energy industry: that electricity delivered by the grid is generally the least expensive option.

Elisa Wood
speed to power

Ameresco and VoltaGrid Deals Show Investor Appetite for Energy Alternatives

New investments involving VoltaGrid and Ameresco underscore rising demand for behind-the-meter power and renewable natural gas.

Elisa Wood
investor-appetite-for-energy-alternatives

Calling Distributed Energy “Rinky-Dink” Gets the Grid Wrong

Local solar, batteries, EVs and virtual power plants aren’t sideshows. They’re becoming core grid resources.

Elisa Wood
energy abundance
Subscribe to our free weekly newsletter about all things distributed energy.
Subscribe

Top Podcast

Distributed energy utility relationship

The DER-Utility Standoff — and a Way Out

Navneet Trivedi of Vrinda talks about rethinking risk, reliability and the rules of a more distributed grid.

Latest Resources

grid utilization

Grid Utilization – Hype vs Reality

What do we need to understand about grid utilization, and what would it take to measure it? The first step is to understand grid utilization potential, which depends on factors such as equipment vintage, weather, external operating constraints, and more. In this publication, team Vrinda presents key issues, analysis, and recommendations to develop metrics to […]

Energy Changemakers Media Kit – The Voice of Distributed Energy

About Energy ChangemakersEnergy Changemakers is a journalist-led media and content platform built exclusively for the distributed energy and grid-edge market. At its core, the company operates at the intersection of: Our mission is to Educate. Elevate. Amplify.

How Supercaps Can Help Solve the Geopolitical Challenge of Battery Over Deployments

The speed-to-power movement is driving decision-making in the data center industry as it searches for near-term solutions to its power supply needs. The inability of many utilities and wholesale market control areas to bring new capacity on-line in a timely manner has prompted many data centers to go behind-the-meter (BTM) and create microgrids and other […]
Large Load Developers Becoming Their Own Power Suppliers

When the Grid Can’t Keep Up

Headlines are everywhere about the electric grid straining under a surge in demand from data centers and other large loads. But the more urgent story is: How can the grid evolve to meet this new demand at speed?

RSS feed: Microgrids Now Microgrids Now

  • Texas Judges Back Enchanted Rock Bridge-to-Power Project, With a Catch
  • A Real Community Microgrid, At Last?
  • Inspiring Tales of Microgrid Innovation at the Top of the World
  • Senate Bill Would Give Microgrids $700M Boost, Try to Pin Down Elusive Value of Resilience
  • The $388 Billion Argument for Data Center Microgrids & Resilience Investments
The Voice of Distributed Energy
Learn about grid edge opportunities
Subscribe
Energy Changemakers
Energy Changemakers
600 Twentyninth Place Ct #1055
Charlottesville, VA 22901
elisa@energychangemakers.com
© Wood Energy Writers LLC. All rights reserved.
  • Terms of Service
  • Privacy Policy